EMIR Installation and Commissioning at the IRAM 30m telescope
Line 3: Line 2:
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
|| 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || ||
|| || || Transport || Truck || Bernard || || ||
|| || || || Helicopter || Javier || || ||
|| 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 14 || 31.3.-7.4. || Commissioning (Week #1) || || Clemens || Carsten || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 15 || 7.4.-14.4. || || || || || ||
|| 16 || 14.4.-21.4. || Commissioning (Week #2) || || Carsten || Clemens || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 17 || 21.4.-28.4. || TBA || || || || ||
note that this page is not maintained anymore (CK)
Line 21: Line 4:
cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
Line 25: Line 5:
The maximum number of people of the EMIR installation team at the 30m, will be '''about 6 only'''.
During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD.
Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
=== Timeline of Installation and Commissioning at the IRAM 30m telescope ===
 * the EMIR homepage for IRAM staff is [[https://gra-lx1.iram.es/mainWiki/EmirProject|here]]
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
||||||||||||||<style="text-align: center;"> ||
|| 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || ||
|| || || Transport || Truck/JYC:12.-15.3. || || || ||
|| || || || Helicopter/16.3. || Javier || || ||
|| || || || || || || ||
|| 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves (16.-), Bruno (16.-), Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien (16.-), Walter || Albrecht, Hans, Helmut ||
|| || || || || || || ||
|| 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing''' || || Santiago || Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.) || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software / Astronomy || || Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-) || Hans, Helmut ||
|| || || || Operator Training || Manolo || || ||
|| || || || || || || ||
||||||||||||||<style="text-align: center;"> ||
|| 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon) || ||
|| || || || Software / Astronomy || || Hans, Clemens(-Fri), Helmut(Tue-Fri) || Walter, Albrecht, Gabriel ||
|| || || || Operator Training || Manolo || || ||
|| || || || || || || ||
|| 15 || 7.4.-14.4. || 24 hours MAMBO2 pooled observations & Full Moon with EMIR || || || Breezy Ocana Flaquer(Mon-Tue) || ||
|| || || || || || || ||
|| 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten(Di-Mo) || Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri) || ||
|| || || || Software / Astronomy || || || Helmut, Walter, Albrecht, Hans ||
|| || || || || || || ||
|| 17 || 21.4.-28.4. || '''#6: Commissioning & MAMBO Pool Observations''' || || Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di) || || Helmut, Gabriel ||

cf. also with

 * [[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule|AoD Schedule]],
 * [[http://www.iram.es/IRAMES/groups/operator/opesched.htm|Operator Schedule]], and
 * [[http://www.iram.es/IRAMES/mainWiki/PoolW0809|schedule of MAMBO pooled observations]]
The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:

 * Night time: Saturn (to 60deg elev)
 * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 * Full moon: 9.4.

note that this page is not maintained anymore (CK)

Timeline of Installation and Commissioning at the IRAM 30m telescope

  • the EMIR homepage for IRAM staff is here

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Transport

Truck/JYC:12.-15.3.

Helicopter/16.3.

Javier

12

17.3.-24.3.

#2: Installation

Santiago

Jean-Yves (16.-), Bruno (16.-), Dave

IF

Salvador, Gabriel

Software

Sebastien (16.-), Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: First Light & Hardware Testing

Santiago

Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.)

IF

Salvador, Gabriel

Software / Astronomy

Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-)

Hans, Helmut

Operator Training

Manolo

14

31.3.-7.4.

#4: Commissioning

Carsten

Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon)

Software / Astronomy

Hans, Clemens(-Fri), Helmut(Tue-Fri)

Walter, Albrecht, Gabriel

Operator Training

Manolo

15

7.4.-14.4.

24 hours MAMBO2 pooled observations & Full Moon with EMIR

Breezy Ocana Flaquer(Mon-Tue)

16

14.4.-21.4.

#5: Commissioning

Carsten(Di-Mo)

Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri)

Software / Astronomy

Helmut, Walter, Albrecht, Hans

17

21.4.-28.4.

#6: Commissioning & MAMBO Pool Observations

Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di)

Helmut, Gabriel

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:

  • Night time: Saturn (to 60deg elev)
  • Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
  • Full moon: 9.4.