EMIR Installation and Commissioning at the IRAM 30m telescope | [https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope |
Line 5: | Line 5: |
|| 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || || | || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || |
Line 8: | Line 8: |
|| 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || || | || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago & Bernard || Dave || || |
Line 11: | Line 11: |
|| 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || || | || 13 || 24.3.-31.3. || '''#3: Hardware Testing & First Light''' || || Santiago & Bernard || Dave || || |
Line 14: | Line 14: |
|| 14 || 31.3.-7.4. || Commissioning (Week #1) || || Clemens || Carsten || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || |
|| 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' (Week #1) || || Clemens || Carsten || || || || || || Software || || Albrecht || Walter, Hans, Helmut || |
Line 17: | Line 17: |
|| 16 || 14.4.-21.4. || Commissioning (Week #2) || || Carsten || Clemens || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || |
|| 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' (Week #2) || || Carsten || Clemens || || || || || || Software || || Hans || Walter, Albrecht, Helmut || |
Line 24: | Line 24: |
The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. |
[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
11 |
10.3.-17.3. |
#1: ABCD Dismounting |
|
Santiago |
Dave, Gregorio, Pako |
|
|
|
Transport |
Truck |
Bernard |
|
|
|
|
|
Helicopter |
Javier |
|
|
12 |
17.3.-24.3. |
#2: Installation |
|
Santiago & Bernard |
Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien, Walter |
Albrecht, Hans, Helmut |
13 |
24.3.-31.3. |
#3: Hardware Testing & First Light |
|
Santiago & Bernard |
Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien, Walter |
Albrecht, Hans, Helmut |
14 |
31.3.-7.4. |
#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #1) |
|
Clemens |
Carsten |
|
|
|
|
Software |
|
Albrecht |
Walter, Hans, Helmut |
15 |
7.4.-14.4. |
|
|
|
|
|
16 |
14.4.-21.4. |
#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #2) |
|
Carsten |
Clemens |
|
|
|
|
Software |
|
Hans |
Walter, Albrecht, Helmut |
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.