Line 8: Line 8:
|| 12 || 17.3.-24.3. || Installation || || Santiago/Bernard || || || || 12 || 17.3.-24.3. || Installation || || Santiago/Bernard || Dave || ||
Line 10: Line 10:
|| 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago/Bernard || || || || 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago/Bernard || Dave || ||

EMIR Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

ABCD Dismounting

Santiago

Transport

Truck

Bernard

Helicopter

Javier

12

17.3.-24.3.

Installation

Santiago/Bernard

Dave

Software

Walter, Albrecht, Hans, Helmut

13

24.3.-31.3.

Hardware Testing & First Light

Santiago/Bernard

Dave

Software

Walter, Albrecht, Hans, Helmut

14

31.3.-7.4.

Commissioning (Week #1)

Clemens

Carsten

Software

Walter, Albrecht, Hans, Helmut

15

7.4.-14.4.

16

14.4.-21.4.

Commissioning (Week #2)

Carsten

Clemens

Software

Walter, Albrecht, Hans, Helmut

17

21.4.-28.4.

TBA

cf. also with