Week ; Dates ; Main Task ; Details ; Lead ; People ;
11;10.3.-17.3.; ABCD Dismounting ; ; ;
  ; ; Transport ; ; ;
12; 17.3.-24.3.; EMIR Installation ; ; ;
13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; ;
14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; ;
15; 7.4.-14.4.; Semana Santa ; ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; ;
17; 21.4.-28.4.; TBA ; ; ;
}}}
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
|| 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || ||
|| || || Transport || Truck || Bernard || || ||
|| || || || Helicopter || Javier || || ||
|| 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 14 || 31.3.-7.4. || Commissioning (Week #1) || || Clemens || Carsten || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 15 || 7.4.-14.4. || || || || || ||
|| 16 || 14.4.-21.4. || Commissioning (Week #2) || || Carsten || Clemens || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 17 || 21.4.-28.4. || TBA || || || || ||

cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]

EMIR Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

ABCD Dismounting

Santiago

Dave, Gregorio, Pako

Transport

Truck

Bernard

Helicopter

Javier

12

17.3.-24.3.

Installation

Santiago & Bernard

Dave

Software

Walter, Albrecht, Hans, Helmut

13

24.3.-31.3.

Hardware Testing & First Light

Santiago & Bernard

Dave

Software

Walter, Albrecht, Hans, Helmut

14

31.3.-7.4.

Commissioning (Week #1)

Clemens

Carsten

Software

Walter, Albrecht, Hans, Helmut

15

7.4.-14.4.

16

14.4.-21.4.

Commissioning (Week #2)

Carsten

Clemens

Software

Walter, Albrecht, Hans, Helmut

17

21.4.-28.4.

TBA