|| '''Week''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">People at the 30m || Standby in Granada || || '''Week''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||

EMIR Installation and Commissioning at the IRAM 30m telescope

Week

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

ABCD Dismounting

SN

Transport

12

17.3.-24.3.

EMIR Installation

SN/BL

WB,AS,HU,HW

13

24.3.-31.3.

EMIR Hardware Testing & First Light

SN/BL

WB,AS,HU,HW

14

31.3.-7.4.

EMIR Commissioning (Week #1)

CT

CK

WB,AS,HU,HW

15

7.4.-14.4.

16

14.4.-21.4.

EMIR Commissioning (Week #2)

CK

CT

WB,AS,HU,HW

17

21.4.-28.4.

TBA