EMIR Installation and Commissioning at the IRAM 30m telescope
Week |
Dates |
Main Task |
Details |
<style="text-align: center;">People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
11 |
10.3.-17.3. |
ABCD Dismounting |
|
SN |
|
|
|
|
Transport |
|
|
|
|
12 |
17.3.-24.3. |
EMIR Installation |
|
SN/BL |
|
|
13 |
24.3.-31.3. |
EMIR Hardware Testing & First Light |
|
SN/BL |
|
|
14 |
31.3.-7.4. |
EMIR Commissioning (Week #1) |
|
CT |
CK |
|
15 |
7.4.-14.4. |
|
|
|
|
|
16 |
14.4.-21.4. |
EMIR Commissioning (Week #2) |
|
CK |
CT |
|
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]