Line 3: Line 3:
|| '''Week''' || '''Dates''' || '''Main Task''' || '''Details''' || '''Lead''' || '''People''' ||
|| 11 || 10.3.-17.3. || ABCD Dismounting || || SN || ||
|| || || Transport || || || ||
|| 12 || 17.3.-24.3. || EMIR Installation || || SN/BL || ||
|| 13 || 24.3.-31.3. || EMIR Hardware Testing & First Light || || SN/BL || ||
|| 14 || 31.3.-7.4. || EMIR Commissioning (Week #1) || || CT || CK ||
|| 15 || 7.4.-14.4. || || || || ||
|| 16 || 14.4.-21.4. || EMIR Commissioning (Week #2) || || CK || CT ||
|| 17 || 21.4.-28.4. || TBA || || || ||
|| '''Week''' || '''Dates''' || '''Main Task''' || '''Details''' |||| <style="text-align: center;">People at the 30m || Standby in Granada ||
|| || || || || '''Lead''' || '''People''' ||
||
|| 11 || 10.3.-17.3. || ABCD Dismounting || || SN || || ||
|| || || Transport || || ||  || ||
|| 12 || 17.3.-24.3. || EMIR Installation || || SN/BL || || ||
|| 13 || 24.3.-31.3. || EMIR Hardware Testing & First Light || || SN/BL || || ||
|| 14 || 31.3.-7.4. || EMIR Commissioning (Week #1) || || CT || CK || ||
|| 15 || 7.4.-14.4. || || ||  || || ||
|| 16 || 14.4.-21.4. || EMIR Commissioning (Week #2) || || CK || CT || ||
|| 17 || 21.4.-28.4. || TBA || || || || ||

EMIR Installation and Commissioning at the IRAM 30m telescope

Week

Dates

Main Task

Details

<style="text-align: center;">People at the 30m

Standby in Granada

Lead

People

11

10.3.-17.3.

ABCD Dismounting

SN

Transport

12

17.3.-24.3.

EMIR Installation

SN/BL

13

24.3.-31.3.

EMIR Hardware Testing & First Light

SN/BL

14

31.3.-7.4.

EMIR Commissioning (Week #1)

CT

CK

15

7.4.-14.4.

16

14.4.-21.4.

EMIR Commissioning (Week #2)

CK

CT

17

21.4.-28.4.

TBA

cf. also with

EmirPlanning (last edited 2009-11-17 08:30:21 by lt-ck)