Differences between revisions 101 and 102
Revision 101 as of 2009-03-09 15:10:17
Size: 3669
Editor: visitor8
Comment:
Revision 102 as of 2009-03-09 15:10:46
Size: 3657
Editor: visitor8
Comment:
Deletions are marked like this. Additions are marked like this.
Line 23: Line 23:
|| || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht || || || || || Software / Astronomy || || Hans || Walter, Hans, Helmut, Albrecht ||
Line 29: Line 29:
|| || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans || || || || || Software / Astronomy || || Helmut || Walter, Albrecht, Hans ||

Timeline of Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

Installation Plan of SN: attachment:Plan001.pdf

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Transport

Truck/JYC:12.-15.3.

Helicopter/16.3.

Javier

12

17.3.-24.3.

#2: Installation

Santiago

Jean-Yves (16.-), Bruno (16.-), Dave

IF

Salvador, Gabriel

Software

Sebastien (16.-), Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: First Light & Hardware Testing

Santiago

Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-27.3.)???

IF

Salvador, Gabriel

Software / Astronomy

Sebastien(-26.), Walter, Albrecht, Clemens(28.3.-)

Hans, Helmut, Juan for the weekend

Operator Training

Manolo

[https://gra-lx1.iram.es/mainWiki/EmirInstallationAndCommissioningPlan Commissioning Plan of CK]

14

31.3.-7.4.

#4: Commissioning

Carsten

Dirk Muders, Sascha Trippe, Clemens(-3.4.)

Software / Astronomy

Hans

Walter, Hans, Helmut, Albrecht

Operator Training

Manolo

15

7.4.-14.4.

16

14.4.-21.4.

#5: Commissioning

Carsten

Clemens, Albert, Melanie

Software / Astronomy

Helmut

Walter, Albrecht, Hans

17

21.4.-28.4.

TBA

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:

  • Night time: Saturn (to 60deg elev)
  • Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
  • Full moon: 9.4.

EmirPlanning (last edited 2009-11-17 08:30:21 by lt-ck)