=== Timeline of Installation and Commissioning at the IRAM 30m telescope ===
Line 2: Line 3:
EMIR Installation and Commissioning at the IRAM 30m telescope  * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]
Line 4: Line 5:
{{{
#!CSV
Week ; Dates ; Main Task ; Details ; People
11;10.3.-17.3.; ABCD Dismounting ; ;
  ; ; Transport ; ;
12; 17.3.-24.3.; EMIR Installation ; ;
13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ;
14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ;
15; 7.4.-14.4.; Semana Santa ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ;
17; 21.4.-28.4.; TBA ; ;
}}}
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
|| 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || ||
|| || || IF-Cable exchange, Painting of receiver cabin || || || || ||
|| || || Transport || Truck/JYC:12.-15.3. || || || ||
|| || || || Helicopter/JL:16.3. || || || ||
|| || || || || || || ||
|| 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves, Bruno, Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| || || || || || || ||
|| 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure(23.-31.), Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software / Astronomy || || Sebastien, Walter, Albrecht || Hans, Helmut ||
|| || || || Operator Training || Manolo || || ||
|| || || || || || || ||
|| 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Dirk Muders, Clemens || ||
|| || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht ||
|| || || || Operator Training || Manolo || || ||
|| || || || || || || ||
|| 15 || 7.4.-14.4. || || || || || ||
|| || || || || || || ||
|| 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens, Albert || ||
|| || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans ||
|| || || || || || || ||
|| 17 || 21.4.-28.4. || TBA || || || || ||

cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
 * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]

The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:
 * Night time: Saturn (to 60deg elev)
 * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 * Full moon: 9.4.

Timeline of Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Dave, Gregorio, Pako

IF-Cable exchange, Painting of receiver cabin

Transport

Truck/JYC:12.-15.3.

Helicopter/JL:16.3.

12

17.3.-24.3.

#2: Installation

Santiago

Jean-Yves, Bruno, Dave

IF

Salvador, Gabriel

Software

Sebastien, Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: First Light & Hardware Testing

Santiago

Jean-Yves, Anne-Laure(23.-31.), Dave

IF

Salvador, Gabriel

Software / Astronomy

Sebastien, Walter, Albrecht

Hans, Helmut

Operator Training

Manolo

14

31.3.-7.4.

#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]

Carsten

Dirk Muders, Clemens

Software / Astronomy

Hans + TBC

Walter, Hans, Helmut, Albrecht

Operator Training

Manolo

15

7.4.-14.4.

16

14.4.-21.4.

#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]

Carsten

Clemens, Albert

Software / Astronomy

Helmut + TBC

Walter, Albrecht, Hans

17

21.4.-28.4.

TBA

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:

  • Night time: Saturn (to 60deg elev)
  • Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
  • Full moon: 9.4.