Week ; Dates ; Main Task ; Details ; People
11;10.3.-17.3.; ABCD Dismounting ; ;
  ; ; Transport ; ;
12; 17.3.-24.3.; EMIR Installation ; ;
13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ;
14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ;
15; 7.4.-14.4.; Semana Santa ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ;
17; 21.4.-28.4.; TBA ; ;
}}}
| Week | Dates | Main Task | Details | Lead | People |
| 11 | 10.3.-17.3. | ABCD Dismounting | | SN | |
| | | Transport | | | |
| 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | |
| 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | |
| 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | |
| 15 | 7.4.-14.4. | | | | | | |
| 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
| 17 | 21.4.-28.4. | TBA | | | | | |

cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]

EMIR Installation and Commissioning at the IRAM 30m telescope

| Week | Dates | Main Task | Details | Lead | People | | 11 | 10.3.-17.3. | ABCD Dismounting | | SN | | | | | Transport | | | | | 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | | | 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | | | 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | | | 15 | 7.4.-14.4. | | | | | | | | 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | | | 17 | 21.4.-28.4. | TBA | | | | | |