457
Comment:
|
3075
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope | |
Line 2: | Line 3: |
EMIR Installation and Commissioning at the IRAM 30m telescope | || '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck || Jean-Yves || || || || || || || Helicopter || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago/Bernard? || Jean-Yves?, Dave, Anne-Laure? || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Bernard?/Santiago || Anne-Laure?, Dave, Jean-Yves? || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien, Walter, Albrecht || Hans, Helmut || || || || || || || || || || || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Clemens || Carsten || || || || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht || || || || || || || || || || 15 || 7.4.-14.4. || || || || || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens || || || || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || TBA || || || || || |
Line 4: | Line 27: |
{{{ #!CSV Week ; Dates ; Main Task ; Details ; People 11;10.3.-17.3.; ABCD Dismounting ; ; ; ; Transport ; ; 12; 17.3.-24.3.; EMIR Installation ; ; 13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; 14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; 15; 7.4.-14.4.; Semana Santa ; ; 16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; 17; 21.4.-28.4.; TBA ; ; }}} |
cf. also with * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. |
[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
||
|
|
|
|
Lead |
Staff |
Staff |
|
11 |
10.3.-17.3. |
#1: ABCD Dismounting |
|
Santiago |
Dave, Gregorio, Pako |
|
|
|
|
Transport |
Truck |
Jean-Yves |
|
|
|
|
|
|
Helicopter |
Javier |
|
|
|
|
|
|
|
|
|
|
|
12 |
17.3.-24.3. |
#2: Installation |
|
Santiago/Bernard? |
Jean-Yves?, Dave, Anne-Laure? |
|
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
|
Software |
|
Sebastien, Walter |
Albrecht, Hans, Helmut |
|
|
|
|
|
|
|
|
|
13 |
24.3.-31.3. |
#3: First Light & Hardware Testing |
|
Bernard?/Santiago |
Anne-Laure?, Dave, Jean-Yves? |
|
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
|
Software / Astronomy |
|
Sebastien, Walter, Albrecht |
Hans, Helmut |
|
|
|
|
|
|
|
|
|
14 |
31.3.-7.4. |
#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] |
|
Clemens |
Carsten |
|
|
|
|
|
Software / Astronomy |
|
Hans + TBC |
Walter, Hans, Helmut, Albrecht |
|
|
|
|
|
|
|
|
|
15 |
7.4.-14.4. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 |
14.4.-21.4. |
#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] |
|
Carsten |
Clemens |
|
|
|
|
|
Software / Astronomy |
|
Helmut + TBC |
Walter, Albrecht, Hans |
|
|
|
|
|
|
|
|
|
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
[http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.