| [https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope | |
| Line 2: | Line 3: | 
| EMIR Installation and Commissioning at the IRAM 30m telescope | || '''#''' || '''Dates'''       || '''Main Task'''        || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck || Jean-Yves || || || || || || || Helicopter || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago/Bernard? || Jean-Yves?, Dave, Anne-Laure? || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Bernard?/Santiago || Anne-Laure?, Dave, Jean-Yves? || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Hans, Helmut || || || || || Astronomy || || Albrecht || || || || || || || || || || || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' (Week #1) || || Clemens || Carsten || || || || || || Software || || Hans || Walter, Hans, Helmut, Albrecht || || || || || || || || || || 15 || 7.4.-14.4. || || || || || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' (Week #2) || || Carsten || Clemens || || || || || || Software || || Helmut || Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || TBA || || || || || | 
| Line 4: | Line 28: | 
| {{{ #!CSV Week ; Dates ; Main Task ; Details ; People 11;10.3.-17.3.; ABCD Dismounting ; ; ; ; Transport ; ; 12; 17.3.-24.3.; EMIR Installation ; ; 13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; 14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; 15; 7.4.-14.4.; Semana Santa ; ; 16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; 17; 21.4.-28.4.; TBA ; ; }}} | cf. also with * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. | 
[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope
| # | Dates | Main Task | Details | People at the 30m | Standby in Granada | |
| 
 | 
 | 
 | 
 | Lead | Staff | Staff | 
| 11 | 10.3.-17.3. | #1: ABCD Dismounting | 
 | Santiago | Dave, Gregorio, Pako | 
 | 
| 
 | 
 | Transport | Truck | Jean-Yves | 
 | 
 | 
| 
 | 
 | 
 | Helicopter | Javier | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 12 | 17.3.-24.3. | #2: Installation | 
 | Santiago/Bernard? | Jean-Yves?, Dave, Anne-Laure? | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software | 
 | Sebastien, Walter | Albrecht, Hans, Helmut | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 13 | 24.3.-31.3. | #3: First Light & Hardware Testing | 
 | Bernard?/Santiago | Anne-Laure?, Dave, Jean-Yves? | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software | 
 | Sebastien, Walter | Hans, Helmut | 
| 
 | 
 | 
 | Astronomy | 
 | Albrecht | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 14 | 31.3.-7.4. | #4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #1) | 
 | Clemens | Carsten | 
 | 
| 
 | 
 | 
 | Software | 
 | Hans | Walter, Hans, Helmut, Albrecht | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 15 | 7.4.-14.4. | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 16 | 14.4.-21.4. | #5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #2) | 
 | Carsten | Clemens | 
 | 
| 
 | 
 | 
 | Software | 
 | Helmut | Walter, Albrecht, Hans | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 17 | 21.4.-28.4. | TBA | 
 | 
 | 
 | 
 | 
cf. also with
- [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and 
- [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] 
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.