Differences between revisions 1 and 28 (spanning 27 versions)
Revision 1 as of 2009-02-03 10:45:38
Size: 457
Editor: visitor3
Comment:
Revision 28 as of 2009-02-03 11:51:38
Size: 2354
Editor: visitor3
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
Line 4: Line 3:
{{{
#!CSV
Week ; Dates ; Main Task ; Details ; People
11;10.3.-17.3.; ABCD Dismounting ; ;
  ; ; Transport ; ;
12; 17.3.-24.3.; EMIR Installation ; ;
13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ;
14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ;
15; 7.4.-14.4.; Semana Santa ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ;
17; 21.4.-28.4.; TBA ; ;
}}}
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
|| 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || ||
|| || || Transport || Truck || Bernard || || ||
|| || || || Helicopter || Javier || || ||
|| 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 14 || 31.3.-7.4. || Commissioning (Week #1) || || Clemens || Carsten || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 15 || 7.4.-14.4. || || || || || ||
|| 16 || 14.4.-21.4. || Commissioning (Week #2) || || Carsten || Clemens || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 17 || 21.4.-28.4. || TBA || || || || ||

cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]

The maximum number of people of the EMIR installation team at the 30m, will be '''about 6 only'''.
During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD.
Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

EMIR Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

ABCD Dismounting

Santiago

Dave, Gregorio, Pako

Transport

Truck

Bernard

Helicopter

Javier

12

17.3.-24.3.

Installation

Santiago & Bernard

Dave

IF

Salvador, Gabriel

Software

Sebastien, Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

Hardware Testing & First Light

Santiago & Bernard

Dave

IF

Salvador, Gabriel

Software

Sebastien, Walter

Albrecht, Hans, Helmut

14

31.3.-7.4.

Commissioning (Week #1)

Clemens

Carsten

Software

Walter, Albrecht, Hans, Helmut

15

7.4.-14.4.

16

14.4.-21.4.

Commissioning (Week #2)

Carsten

Clemens

Software

Walter, Albrecht, Hans, Helmut

17

21.4.-28.4.

TBA

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be about 6 only. During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.