Week ; Dates ; Main Task ; Details ; People 11;10.3.-17.3.; ABCD Dismounting ; ; ; ; Transport ; ; 12; 17.3.-24.3.; EMIR Installation ; ; 13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; 14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; 15; 7.4.-14.4.; Semana Santa ; ; 16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; 17; 21.4.-28.4.; TBA ; ; |
Week ; Dates ; Main Task ; Details ; Lead ; People ; 11;10.3.-17.3.; ABCD Dismounting ; ; ; ; ; Transport ; ; ; 12; 17.3.-24.3.; EMIR Installation ; ; ; 13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; ; 14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; ; 15; 7.4.-14.4.; Semana Santa ; ; ; 16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; ; 17; 21.4.-28.4.; TBA ; ; ; |
EMIR Installation and Commissioning at the IRAM 30m telescope