We have checked all the thermometry, installed and plugged the last cryogenics parts. Then we have closed the NIKA2 cryostat putting super insulation on each screen, one after the other. This was quite time consuming and took most of the day. Once the cryostat was closed, and leak tested we have started to pump on it. In the meantime we have cut at the convenient length the pipe for the 40 lines of tones to be plugged to the cryostat and to the electronics. We have prepared the shelve for the electronics, and plugged the water cooling system to the compressors. And finaly, tonight we have started cooling down the cryostat !
<<BR>>
{{attachment:150930_18_NIKA2_opened_with_shield.JPG||height=215}} {{attachment:151001_1_cutting_super_insulation.JPG||height=215}} {{attachment:151001_2_warping_super_insulation_around_NIKA2_screens.JPG||height=215}} {{attachment:151001_3_warping_super_insulation_around_NIKA2_cold_mirrors_box.JPG||height=215}} {{attachment:151001_4_installing_screen_around_cold_mirrors_box.JPG||height=215}} {{attachment:151001_5_all_pipes_and_cables_plugged on_cryostat.JPG||height=215}} {{attachment:151001_6_contortion_to_fix_super_insulated_cold_mirrors_screen.JPG||height=215}} {{attachment:151001_7_closing_NIKA2_nose.JPG||height=215}} {{attachment:151001_8_NIKA2_closed_with_laser_plate_and_spectrometer.JPG||height=215}} {{attachment:151001_9_pipe_for_the_40_lines_of_tones_cut_at_convenient_length.JPG||height=215}} {{attachment:151001_10_preparing_electronics_shelve.JPG||height=215}} {{attachment:151001_11_NIKA2_with_M5-M6_opened.JPG||height=215}} {{attachment:151001_12_pulse_tubes_interface_NIKA2_starts_cooling_down.JPG||height=215}}

Back to the NIKA2 run 1 main page

September 2015, 24

The 2 1st trucks transporting NIKA2 hardware have arrived at the telescope, and have been unloaded.
The 3rd truck containing the cryostat and driven by Alessandro, Martino and Andrea will arrive on Tuesday 29 in the morning. Alain, Samuel and Johannes will also arrive on Tuesday morning.

September 2015, 29

Everybody has arrived at the telescope this morning: Alessandro, Andrea and Martino with the truck, Alain, Johannes and Samuel with the IRAM transport, with some Granada staff (Santiago, Juan, Dave, Gregorio, etc) who will help installing NIKA2.
There's about 2 tons of material to install. We have installed about half of it: compressors and dilution pump in the cable spiral room, automat (cryogenics control) and pulse tub cold heads on the wall in the receiver cabin, optical fibre switch, some electronics and computers in the control room, He pipes at intermediate stage, plug and test communication with these hardware.
150929_1_NIKA2_boxes_in_garage.JPG 150929_2_NIKA2_noze_in_garage.JPG 150929_3_ready_to_lift_compressor_dilution-pump_and_box.JPG 150929_4_unloading_NIKA2_cryostat_from_truck.JPG 150929_5_lifting_up_He_pipes.JPG 150929_6_preparing_cabin_wall_for_cryogenic_head_and_automat.JPG 150929_7_compressors_and_dilution_bench_in_cable-spiral-room.JPG 150929_8_pulse-tube-cold-head_cryogenics-automat_on_cabin_wall.JPG 150929_9_testing_electronics_in_control_room.JPG

September 2015, 30

1st big operation of the day: we have lifted the NIKA2 cryostat up in the cabin and installed it at its nominal position. 2nd big operation: we have installed the He pipes: from the instrument, down along the azimuth column to the cable spiral and then to the compressors. We have also plugged all the pipes, lifted the cryostat nose, lifted the polariser wheel, installed bars, rails, pulse tubes cold heads, opened and check the screens of the cryostat down to the detector holder frame.
150930_1_ready_to_lift_NIKA2_cryostat.JPG 150930_2_NIKA2_cryostat_through_trapdoor.JPG 150930_3_future_location_of_NIKA2.JPG 150930_4_tilting_NIKA2_from_vertical_to_horizontal.JPG 150930_5_sliding_NIKA2_in_corridor_passing_EMIR.JPG 150930_6_NIKA2_turned_toward_its_final_location.JPG 150930_7_NIKA2_cryostat_at_destination.JPG 150930_8_install_He_pipes_along_azimuth_column_and_cable_spiral.JPG 150930_9_He_pipes_from_cable_spiral_to_compressors_corner.JPG 150930_10_5_pipes_2_compressors_1_dilution_fridge_bench.JPG 150930_11_lifting_NIKA2_nose.JPG 150930_12_lifting_polariser_wheel.JPG 150930_13_hole_for_pulse_tube_head_on_NIKA2.JPG 150930_14_installing_pulse_tube_head_on_NIKA2.JPG 150930_15_cryogenics_pipes_plugged_on_NIKA2.JPG 150930_16_opening_NIKA2_cryostat.JPG 150930_17_100mK_optics_and_detectors_frame.JPG

October 2015, 01

We have checked all the thermometry, installed and plugged the last cryogenics parts. Then we have closed the NIKA2 cryostat putting super insulation on each screen, one after the other. This was quite time consuming and took most of the day. Once the cryostat was closed, and leak tested we have started to pump on it. In the meantime we have cut at the convenient length the pipe for the 40 lines of tones to be plugged to the cryostat and to the electronics. We have prepared the shelve for the electronics, and plugged the water cooling system to the compressors. And finaly, tonight we have started cooling down the cryostat !
150930_18_NIKA2_opened_with_shield.JPG 151001_1_cutting_super_insulation.JPG 151001_2_warping_super_insulation_around_NIKA2_screens.JPG 151001_3_warping_super_insulation_around_NIKA2_cold_mirrors_box.JPG 151001_4_installing_screen_around_cold_mirrors_box.JPG 151001_5_all_pipes_and_cables_plugged on_cryostat.JPG 151001_6_contortion_to_fix_super_insulated_cold_mirrors_screen.JPG 151001_7_closing_NIKA2_nose.JPG 151001_8_NIKA2_closed_with_laser_plate_and_spectrometer.JPG 151001_9_pipe_for_the_40_lines_of_tones_cut_at_convenient_length.JPG 151001_10_preparing_electronics_shelve.JPG 151001_11_NIKA2_with_M5-M6_opened.JPG 151001_12_pulse_tubes_interface_NIKA2_starts_cooling_down.JPG