== September 2015, 29 ==
Line 12: Line 13:
== September 2015, 29 == Everybody has arrived at the telescope this morning: Alessandro, Andrea and Martino with the truck, Alain, Johannes and Samuel with the IRAM transport, with some Granada staff (Santiago, Juan, Dave, Gregorio, etc) who will help installing NIKA2.<<BR>>
There's about 2 tons of material to install. We have installed about half of it: compressors and dilution pump in the cable spiral room, automat (cryogenics control) and pulse tub cold heads on the wall in the receiver cabin, optical fibre switch, some electronics and computers in the control room, He pipes at intermediate stage, plug and test communication with these hardware.
<<BR>>
{{attachment:150929_1_NIKA2_boxes_in_garage.JPG||height=215}} {{attachment:150929_2_NIKA2_noze_in_garage.JPG||height=215}} {{attachment:150929_3_ready_to_lift_compressor_dilution-pump_and_box.JPG||height=215}} {{attachment:150929_4_unloading_NIKA2_cryostat_from_truck.JPG||height=215}} {{attachment:150929_5_lifting_up_He_pipes.JPG||height=215}} {{attachment:150929_6_preparing_cabin_wall_for_cryogenic_head_and_automat.JPG||height=215}} {{attachment:150929_7_compressors_and_dilution_bench_in_cable-spiral-room.JPG||height=215}} {{attachment:150929_8_pulse-tube-cold-head_cryogenics-automat_on_cabin_wall.JPG||height=215}} {{attachment:150929_9_testing_electronics_in_control_room.JPG||height=215}}
<<BR>>

== September 2015, 30 ==

1<sup>st</sup> big operation of the day: we have lifted the NIKA2 cryostat up in the cabin and installed it at its nominal position. 2<sup>nd</sup> big operation: we have also installed the He pipes: from the instrument, down along the azimuth column to the cable spiral and then to the compressors.

Back to the NIKA2 run 1 main page

September 2015, 24

The 2 1st trucks transporting NIKA2 hardware have arrived at the telescope, and have been unloaded.
The 3rd truck containing the cryostat and driven by Alessandro, Martino and Andrea will arrive on Tuesday 29 in the morning. Alain, Samuel and Johannes will also arrive on Tuesday morning.

September 2015, 29

Everybody has arrived at the telescope this morning: Alessandro, Andrea and Martino with the truck, Alain, Johannes and Samuel with the IRAM transport, with some Granada staff (Santiago, Juan, Dave, Gregorio, etc) who will help installing NIKA2.
There's about 2 tons of material to install. We have installed about half of it: compressors and dilution pump in the cable spiral room, automat (cryogenics control) and pulse tub cold heads on the wall in the receiver cabin, optical fibre switch, some electronics and computers in the control room, He pipes at intermediate stage, plug and test communication with these hardware.
150929_1_NIKA2_boxes_in_garage.JPG 150929_2_NIKA2_noze_in_garage.JPG 150929_3_ready_to_lift_compressor_dilution-pump_and_box.JPG 150929_4_unloading_NIKA2_cryostat_from_truck.JPG 150929_5_lifting_up_He_pipes.JPG 150929_6_preparing_cabin_wall_for_cryogenic_head_and_automat.JPG 150929_7_compressors_and_dilution_bench_in_cable-spiral-room.JPG 150929_8_pulse-tube-cold-head_cryogenics-automat_on_cabin_wall.JPG 150929_9_testing_electronics_in_control_room.JPG

September 2015, 30

1<sup>st</sup> big operation of the day: we have lifted the NIKA2 cryostat up in the cabin and installed it at its nominal position. 2<sup>nd</sup> big operation: we have also installed the He pipes: from the instrument, down along the azimuth column to the cable spiral and then to the compressors.