Week |
Dates |
AoD |
Comments |
|
40 |
5.10.-12.10.2010 |
M.Ruiz |
Global 3mm VLBI (7.-12.10.) |
|
41 |
12.10.-19.10. |
J.Abreu & H.Ungerechts (14.-19.10.) |
NIKA arrives on 14.10. |
|
42 |
19.10.-26.10. |
D.Riquelme |
NIKA run + Obs. |
|
43 |
26.10.-2.11. |
G.Quintana-Lacaci (25.-29.10.), C.Buchbender (29.10.-2.11.), J.Abreu (29.10.-5.11.) |
MAMBO2 re-installation & checkout (starts on 25.10.), Poolweek |
|
44 |
2.11.-9.11. |
M.Gonzalez (2.-7.11.) & J.Abreu (29.10.-5.11.), M.Ruiz (8.-9.11., day-time operator) |
HERA Poolweek, HERM33ES workshop 8./9.11. |
|
45 |
9.11.-16.11. |
A.Sievers |
MAMBO2 Poolweek |
|
46 |
16.11.-23.11. |
M.Gonzalez |
HERA Poolweek |
|
47 |
23.11.-30.11. |
J.Abreu |
Reserve Poolweek, End of Summersemester 2010 |
|
48 |
30.11.-7.12. |
C.Buchbender |
+++Start of winter semester 2010/11+++ |
|
49 |
7.12.-14.12. |
D.Riquelme/M.Gonzalez (replacing G.Quintana-Lacaci) |
1st MAMBO2 [[http://www.iram.es/IRAMES/mainWiki/PoolS10|Poolweek|Poolweek]] |
|
50 |
14.12.-21.12. |
M.Gonzalez (F.Damour, day-time-operator) |
1st HERA Poolweek |
|
51 |
21.12.-28.12. |
D.Riquelme (F.Damour, day-time-operator) |
|
|
51 |
28.12.-4.1. |
J.Abreu (J.Santiago, night-time-operator) |
restart of HERA pool on Friday 7.1. |
|
1 |
4.1.2011-11.1. |
C.Buchbender (M.Ruiz, night-time-operator) |
HERA pool week |
|
2 |
11.1.-18.1. |
M.Gonzalez |
HERA pool week |
|
3 |
18.1.-25.1. |
G.Quintana-Lacaci |
MAMBO pool week |
|
4 |
25.1.-1.2. |
H.Ungerechts |
|
|
5 |
1.2.-8.2. |
G.Paubert |
|
|
6 |
8.2.-15.2. |
J.Abreu |
MAMBO pool week |
|
7 |
15.2.-22.2. |
M.Gonzalez |
HERA pool week |
|
8 |
22.2.-1.3. |
G.Quintana-Lacaci |
MAMBO pool week |
|
9 |
1.3.-8.3. |
M.Gonzalez |
HERA pool week |
|
10 |
8.3.-15.3. |
D.Riquelme |
|
|
11 |
15.3.-22.3. |
J.Abreu |
Reserve pool week |
|
12 |
22.3.-29.3. |
C.Buchbender |
228-09 scheduled |
|