Line 21: | Line 21: |
12;17.3.-24.3.;G.Quintana (SB,WB,AS,HU,HW); MAMBO-Pool #4 (night) + EMIR #2: Installation & Hardware testing 13;24.3.-31.3.;D.Riquelme + CT,CK (WB,AS,HU,HW); MAMBO-Pool #5 (few nights) + EMIR #3 Installation & Hardware testing & First Light 14;31.3.-7.4.; (CK,CT,WB,AS,HU,HW); EMIR #4: Commissioning + 30m webcast/100HA on 3.4. |
12;17.3.-24.3.;G.Quintana ; MAMBO-Pool #4 (night) + EMIR #2: Installation & Hardware testing 13;24.3.-31.3.;D.Riquelme ; MAMBO-Pool #5 (few nights) + EMIR #3: Installation & Hardware testing & First Light 14;31.3.-7.4.; C.Kramer; EMIR #4: Commissioning + 30m webcast/100HA on 3.4. |
Line 25: | Line 25: |
16;14.4.-21.4.; (CK,CT,WB,AS,HU,HW); EMIR #5: Commissioning | 16;14.4.-21.4.; C.Kramer; EMIR #5: Commissioning |