note that this page is not maintained anymore (CK) === Timeline of Installation and Commissioning at the IRAM 30m telescope === * the EMIR homepage for IRAM staff is [[https://gra-lx1.iram.es/mainWiki/EmirProject|here]] || '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || |||||||||||||| || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/16.3. || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves (16.-), Bruno (16.-), Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien (16.-), Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing''' || || Santiago || Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.) || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-) || Hans, Helmut || || || || || Operator Training || Manolo || || || || || || || || || || || |||||||||||||| || || 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon) || || || || || || Software / Astronomy || || Hans, Clemens(-Fri), Helmut(Tue-Fri) || Walter, Albrecht, Gabriel || || || || || Operator Training || Manolo || || || || || || || || || || || || 15 || 7.4.-14.4. || 24 hours MAMBO2 pooled observations & Full Moon with EMIR || || || Breezy Ocana Flaquer(Mon-Tue) || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten(Di-Mo) || Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri) || || || || || || Software / Astronomy || || || Helmut, Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || '''#6: Commissioning & MAMBO Pool Observations''' || || Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di) || || Helmut, Gabriel || cf. also with * [[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule|AoD Schedule]], * [[http://www.iram.es/IRAMES/groups/operator/opesched.htm|Operator Schedule]], and * [[http://www.iram.es/IRAMES/mainWiki/PoolW0809|schedule of MAMBO pooled observations]] The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. Planets & Moon during Commissioning: * Night time: Saturn (to 60deg elev) * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter * Full moon: 9.4.