note that this page is not maintained anymore (CK)

Timeline of Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Transport

Truck/JYC:12.-15.3.

Helicopter/16.3.

Javier

12

17.3.-24.3.

#2: Installation

Santiago

Jean-Yves (16.-), Bruno (16.-), Dave

IF

Salvador, Gabriel

Software

Sebastien (16.-), Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: First Light & Hardware Testing

Santiago

Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.)

IF

Salvador, Gabriel

Software / Astronomy

Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-)

Hans, Helmut

Operator Training

Manolo

14

31.3.-7.4.

#4: Commissioning

Carsten

Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon)

Software / Astronomy

Hans, Clemens(-Fri), Helmut(Tue-Fri)

Walter, Albrecht, Gabriel

Operator Training

Manolo

15

7.4.-14.4.

24 hours MAMBO2 pooled observations & Full Moon with EMIR

Breezy Ocana Flaquer(Mon-Tue)

16

14.4.-21.4.

#5: Commissioning

Carsten(Di-Mo)

Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri)

Software / Astronomy

Helmut, Walter, Albrecht, Hans

17

21.4.-28.4.

#6: Commissioning & MAMBO Pool Observations

Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di)

Helmut, Gabriel

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:

EmirPlanning (last edited 2009-11-17 08:30:21 by lt-ck)